In-Pipe SHPP Scheme
1_Poti Water Supply Network
2_Akhaltsikhe Water Supply Network
3_Akhalkalaki Water Supply Network
4_Sadgeri Water Supply Network
Turbine

Consultancy services for in-pipe hydro systems on water supply pipes

Project Description:

Pre-feasibility study and concept development of in-pipe hydropower plants installation in water supply systems, including estimation of energy potential and financial estimation.

Parameters of the four selected locations:

  1. POTI SHPP:
    Head range: 220 m
    Water flow Q=316 L/sec
    Pipe diameter D=500mm
    Distance to line connection point: 30m

  2. AKHALTSIKHE SHPP
    Head range: 310
    Water flow Q=180 L/sec
    Pipe diameter D=426mm
    Distance to line connection point: 100m

  3. AKHALKALAKI SHPP
    Head range: 145 m
    Water flow Q=277 (SUM) L/sec
    Pipe diameter D=250, 319, 400, 500mm (There are 4 parallel pipes and can be united);
    Distance to line connection point: 250m

  4. SADGERI SHPP
    Head range: 200 m
    Water flow Q=160 L/sec
    Pipe diameter D=300 mm
    Distance to line connection point: 150m

The Study included:
Hydraulic calculations and layout
Detailed input data for turbine design
Equipment design
Electric design- single line diagram
Calculation of possible annual energy yield
Generation model
Bill of Quantities
Preliminary BoQ for Civil Works
Preliminary BoQ for Mechanical and Electrical Components
Simplified study & calculation for economic feasibility
Annual cost/payback model for each power plant
Estimate price for generated electricity for 1 Kwh, financial model.
Client:
JDF Georgian Energy Development Fund
Year:
2021
Location:
Georgia - Various Locations

PREVIOUS PROJECT

Feasibility Study of a new hydropower plant and revamping of the existing one in Satriano di Lucania (PZ)

NEXT PROJECT

Owner’s Engineer for the Construction of River Gee Hydropower Plant

RELATED PROJECTS

Pettorina Intake

Pettorina – Sorarù Hydropower Plant

by webmaster
default

Feasibility Study of a new hydropower plant and revamping of the existing one in Satriano di Lucania (PZ)

by webmaster
Immagine21

Vietri (Hotel Loyd) Rockfall

by webmaster

ENCO Engineering Consultants

Via Feltre, 183 – 32036 Sedico (BL)

P (+39) 0437 852727
F (+39) 0437 852717
E info@enco.energy

VAT N: 00607990256

MENU

  • About us
  • Expertise
  • Case studies
  • News
  • Contact us
  • Privacy Policy
  • Cookie Policy
© 2025 Enco Engineering Consultants srl. All rights reserved.
Shopping Basket